Construction update 14 February 2025

14 February 2025

Construction is well underway as we reach our milestones - thanks to our contractors' hard work during the recent heatwaves.

During the last few weeks, they have been busy, with approximately 60% of Whyte Street's pipes installed and around 30% of Tarlton Street's culverts. We have also installed 6 of the 12 stormwater junction boxes.

A range of service relocations have also been required for this project. 90% of these relocations are complete, including SA Water’s sewer realignment on Whyte Street.

Over the next month, the Esplanade/Whyte Street Roundabout will be reinstated.

Finally, residents are encouraged to speak to the contractors on-site about any specific access needs. The contractors try to door-knock and contact residents as they move along. If they are approaching your driveway, we encourage you to please communicate specific access needs with them.

We thank you for your patience while these significant works and associated traffic detours continue.

Culvert along Tarlton Street